Q: I am getting ready to remodel my Kitchen, what is the Normal or expected Deposit for a Contractor these days to get the job started????
Posted in Kitchen on
-
Kyle J from
Remodeling By Classic Homes
Keizer, ORA: Depsit to expect
I usually ask for 25% down at contract signing, with payments in 25% increments.
it can really depend on what kind of job it is and what Materials need to be pre-ordered.
Be weary of contractors that need money up front to purchase materials to get started.
Rating: 0Flag / Report
-
A: Check your State "deposit: allowances
In California a contractor can only ask up to 10% or $1,000 which ever is more. UNLESS they have a showroom, then they can ask for up to 50%.